Skip to main content
How To: Add Phase Change Lines
Updated over 9 months ago

Users can add phase change lines during a tracking session.

To add phase change lines:

  1. Select Track from the bottom navigation bar.

  2. Click the ellipses icon next to a task.

    • If not currently in a tracking session, select a session to Continue on the Track screen before adding a phase change line.

  3. Select Add Target Phase Change Line.

  4. In the "Add Phase Change?" pop-up, Appears After (Date) and Next Phase must be selected.

    • Please note, if moving out of "Not Specified" --> "Baseline," users may want the date to appear the day before.

  5. Click Save & View Graph to generate a line on the graph and update the tracking session.

Did this answer your question?