How to Add Phase Change Lines
Andrew avatar
Written by Andrew
Updated over a week ago

To add phase change lines:

  1. Navigate to the Track screen and click the ellipses

  2. Click Add Phase Change (Graph)

3. In the "Add Phase Change?" pop-up, the Appears After (Date) and Next Phase must be selected.

  • Please note, if moving out of "Not Specified" --> "Baseline," you may want the date to appear the day before.

4. After clicking Save & View Graph, a line is generated on the graph and will change on the tracking session.

Did this answer your question?